The housing society redevelopment guide for Mumbai

A society that follows a documented, fair sequence secures better terms and a decision that holds. A society that skips steps usually discovers why they existed at year three.

For
Housing society committees and members
Reading time
12 min
Updated
20 August 2026
Steps
11

The short answer

A society redevelopment should proceed in order: assess the building's condition, pass a general body resolution to explore redevelopment, commission an independent feasibility study, appoint independent advisers, run a transparent tender, shortlist and diligence developers, select by documented general body decision, negotiate and review the development agreement with both a solicitor and a commercial adviser, obtain approvals, vacate only once security and rent are in place, and monitor construction to possession. Applicable procedural requirements under Maharashtra cooperative law should be confirmed with counsel.

Step by step

The sequence.

  1. Step 01

    Assess the building

    Commission a structural audit so the case for redevelopment rests on evidence rather than opinion.

  2. Step 02

    Resolve to explore

    Pass a properly noticed and minuted general body resolution to explore redevelopment and appoint advisers.

  3. Step 03

    Establish feasibility

    Commission an independent study of development potential, indicative member entitlement, corpus and rent before contacting developers.

  4. Step 04

    Appoint independent advisers

    Appoint a commercial adviser and a solicitor paid by the society, with conflicts disclosed.

  5. Step 05

    Run a transparent tender

    Issue a uniform offer format so that all offers are directly comparable, with an evaluation matrix agreed before opening.

  6. Step 06

    Diligence the shortlist

    Check balance sheets, current commitments, delivery record against committed dates, litigation and how previous society projects ended.

  7. Step 07

    Select by general body decision

    Present the evaluation and recommendation to members and record the decision and reasons.

  8. Step 08

    Negotiate and review the agreement

    Secure carpet definition, corpus security, rent until possession, delay security and a written specification — reviewed commercially and legally.

  9. Step 09

    Obtain approvals

    Track the developer's approval progress against the agreed timeline before members vacate.

  10. Step 10

    Vacate with protections in place

    Vacate only once rent, deposits and security against delay are in place as agreed.

  11. Step 11

    Monitor to possession

    Monitor construction, payments and approvals through to occupation certificate and handover.

The seven terms to compare

Compare every offer on the same basis across all seven — never on carpet area alone.

  • Carpet entitlement, with the exact definition and measurement basis
  • Corpus amount, payment stage and security
  • Rent amount, escalation and continuation until possession
  • Possession timeline and consequence for delay
  • Security — bank guarantee, escrow or mortgage of developer's share
  • Written specification schedule with brands and grades
  • Developer capacity — balance sheet, commitments, delivery record

What makes a decision withstand challenge

Proper notice, accurate minutes, a uniform offer format, an evaluation matrix agreed in advance, recorded reasons and disclosure of any committee member's connection to a bidder. These are tedious and they are the difference between a decision that holds and one that stalls the project later.

This guide is general information only and is not legal, tax or financial advice. Regulations, rates and procedures change; confirm the current position with the relevant authority and a qualified adviser before acting.

Questions

Frequently asked.

How many members must agree to redevelopment?

Consent requirements are set by applicable cooperative law, government directions and the specific scheme, and they have changed over time. Confirm the current requirement for your society with counsel before relying on any figure.

Should members vacate before approvals are received?

Generally not. Vacating before key approvals and before security and rent arrangements are in place transfers delay risk to members. Link vacating to defined approval milestones in the agreement.